project timing with remodel partner is faster
"Timing is a key concern, we produce your project quickly!  So you can get on with your life"
LoginPay Online

HomeAboutServicesWhat's NewPortfolioTestimonialsFundingContact

Copyright 2010 Remodel-Partner, Inc.: Remodeling IL. All Rights Reserved.
Time is money!  We realize that the sooner we plan and build your project the sooner you can get your life back to your normal Chicago suburban life.  Below find an approximate accounting of the time needed to produce an average room addition project.
FREE DESIGN!
     ASK FOR DETAILS
Over 50 years of experience with a RESPECTED TRADITION of QUALITY and DEPENDABILTY
HomeAboutServicesWhat's NewPortfolioTestimonialsFundingContact

CALL NOW! 630-918-9642
Timing

Save Time & Money When You Remodel With Illinois Remodel Partner, Inc

Timing:

The average project

Funding:  From that 1st call funding can take approx 2-4 weeks
Architectural Design:  A few days
Scope of Work:  A couple of days after design is completed
Contract Documents:  After design and scope are determined
Final Plans:  Approx 1 week
Building Permit:  Approx 2-4 weeks (depending on how busy the building dept is)
Project Start:  Approx 1 week after permit issued
Average Construction Time: Approx 2-3 months depending on the scope of work

So the average timing from the 1st consultation to a finished project can be as little as 8 weeks!